Kinmore Green Development

  • Location: Darch, WA
  • Client: TABEC
  • Timeframe-For-Completion: Current Works
  • Contract Value: $8 Million +
  • Stages: 1, 2 & 3

Densford Civil were excited to be awarded three contracts for this project, paving the way for some truly impactful developments. Stage 1 – November 2021 to May 2022; Stage 1B, 2A & 2B – April 2022 to September 2023; Stage 1C & 3 Deep Sewer –  November 2023 to September 2024.

Scope of works included; earthworks, service location, extensive limestone retaining walls, installation of underground services, dewatering and deep sewer, pavement and carpark construction, footpaths, and street lighting install. The team completed the works to a high standard, proving their exceptional capabilities. As a result, Densford Civil were awarded additional contracts.