Staff Carpark A Expansion

  • Location: Perth Airport, WA
  • Client: Perth Airport Pty Ltd
  • Timeframe-For-Completion: 5 Months
  • Contract Value: $1-2 Million

Densford completed parking infrastructure in the Domestic Airport T3/T4 Precinct. This involved integration into and realigning of existing carparks, whilst maintaining user access. Works included; significant service location, installation of underground services, pavement construction, kerbs and footpaths, installation of 30m lighting towers and CCTV poles, and other major electrical works. Densford provided time and cost saving alternatives, completing the works to a high standard with overall client satisfaction.