- Location: Fremantle, WA
- Client: DP World Fremantle Port
- Timeframe-For-Completion: 12 Months
- Contract Value: $8 Million
Densford Civil were awarded the complex infrastructure works for DP World at Fremantle Port. Works included 8000m2 of new pavement for a capacity of 29 trucks for the Truck Marshalling Area, and 11,000m2 of new pavement for 347 new container bays for the Empty Container Parking Area. Scope of works also included; asphalt, trenching and new conduits install, electrical cabling, new fibre install, and switchboard upgrades.
Our crews vast experience working within live operating conditions was imperative for the success of this project as they worked within Fremantle’s live operating Port. Working side by side seamlessly with Fremantle Port and DP World insuring there were no delays to the Port’s productivity and Client’s project timeline.